UAE Solar IPP Finance: Equity, Debt and the Limits of the 60/40 Example

UAE Solar IPP Finance: Equity, Debt and the Limits of the 60/40 Example

UAE clean energy project finance can involve several forms of capital participation, but they should not be treated as equivalent. Equity in a solar project company, a loan financing that project and a bond issued by a renewable energy developer expose capital to different counterparties and contractual rights.

For investors, the starting point is therefore the instrument and legal entity—not an assumed national ownership formula. Al Ajban provides a documented example of a solar IPP structure. Masdar’s recent financing disclosures provide a separate view of capital raised at project and issuer level.

The PPA discussion here concerns utility-offtake arrangements for IPP projects, rather than the corporate clean-power procurement routes used by individual commercial and industrial customers.

For the wider policy framework, procurement routes and project pipeline, start with our UAE renewable energy investment and development guide.

What Al Ajban actually demonstrates

EWEC’s 17 September 2024 announcement describes the financial close of the 1.5 GW AC Al Ajban Solar PV project. The project company is owned by Masdar at 60%, EDF Renewables at 20% and Korea Western Power at 20%. It signed a 30-year PPA with EWEC and is responsible for designing, financing, building and operating the plant. EWEC will procure 100% of its output.

This is evidence for the ownership and offtake arrangements of Al Ajban. It is not sufficient evidence that every UAE renewable energy investment must follow a mandatory 60/40 split.

The distinction matters for foreign developers. A project’s shareholding arrangement needs to be read alongside its procurement documents, shareholder agreement and applicable approvals. A percentage taken from one successful consortium does not establish the rules of a different opportunity.

The same announcement expected full commissioning in the third quarter of 2026. That historical target should not be used as proof that commissioning has occurred; this article uses the release to establish the documented financial-close structure, not the plant’s present operating status.

Project equity, project debt and developer bonds

Capital routeEntity and exposure to examineDocuments central to appraisal
Project equityOwnership interest in the project company and its distributionsShareholder agreement, financial model and project contracts
Project debtBorrower obligations, repayment sources and contractual protectionsFacility agreement, security documents and covenant package
Developer bondObligations of the issuer, plus any guarantees or security specified in the instrumentOffering circular, final terms and issuer disclosures

This is an analytical comparison. The rights of an actual investor or lender depend on the transaction documents; the table does not assert identical structures across all UAE deals.

An equity percentage says how much of a company a shareholder owns. It does not tell an investor the acquisition price, future capital calls, distribution restrictions or expected return. Likewise, a published financing amount does not reveal the full repayment profile or whether every facility has identical terms.

What the PPA supports—and what its headline cannot prove

Al Ajban’s release identifies a long-term customer and contracted procurement of output. Those are relevant facts when assessing the project’s revenue arrangements. However, the release does not reproduce the full PPA or establish every payment condition.

An investor should not automatically replace “EWEC is the offtaker” with “all revenues carry an unconditional sovereign guarantee”. Nor should a 30-year term be treated as proof of take-or-pay, curtailment compensation or a particular termination payment.

The investment work is to connect the revenue provisions to debt service and equity distributions. Questions include when payment is earned, how unavailable generation is treated, what happens during delay, and which liabilities sit with the project company. These questions are not claims that a particular risk has or has not been transferred in Al Ajban.

What public financing disclosures leave open

EWEC names six financial institutions for Al Ajban: BNP Paribas, Crédit Agricole CIB, Standard Chartered, HSBC Middle East, SMBC and KEXIM. The announcement does not publish the full loan terms or debt-to-equity ratio.

For comparison, Masdar’s July 2026 RTC announcement discloses a US$5.1 billion financing package and US$1 billion of equity within a US$6.1 billion project. That information belongs to the RTC case; it should not be transferred to Al Ajban or used as a standard financing ratio for all UAE solar assets.

A useful data-room request distinguishes information that is public, information available under confidentiality and assumptions that remain unverified. Missing detail is not permission to fill the model with an unexplained “market standard”.

Masdar bonds: a different participation route

On 27 October 2026, Masdar announced a US$600 million, five-year blue bond under its US$6 billion Global Medium Term Note Programme. The stated allocation is to maritime renewable energy projects, including offshore wind, under an updated Green Finance Framework.

This is an issuer-level financing example, not an offer of equity in Al Ajban or proof that the proceeds finance the UAE solar projects discussed here. Masdar also reported allocations across ten countries as of year-end 2025, illustrating the international scope of its bond programme.

For a bond investor, eligible use of proceeds and sustainability reporting are separate questions from repayment obligations. The framework should be examined alongside—not instead of—the instrument’s financial terms, issuer credit information and any guarantees or security.

Six checks before committing capital

1. Identify the legal entity and instrument being acquired or financed.

2. Verify the proposed ownership and participation conditions for that specific transaction.

3. Read the revenue agreement without assuming unpublished guarantees or payment protections.

4. Trace cash flows from project operations through debt service to distributions.

5. Identify construction, operating, refinancing and termination risks, and the party carrying each.

6. Separate verified public information from confidential documents and investment-model assumptions.

The opportunity is not a generic promise of risk-free renewable infrastructure. It is a specific transaction whose counterparty, rights, conditions and downside cases can be examined. Keeping those layers distinct is more useful to an investment decision than treating a 60/40 example as a national rule.

Rinnovabili •

About Author / Alessia Bardi

Alessia Bardi is Head of the Green Building and Smart City sections at Rinnovabili, where she develops editorial content and in-depth features on key topics such as energy efficiency, urban innovation, and climate transition. She also manages content strategy for industry events, overseeing their organization with a focus on emerging technologies applied to sustainable construction, smart cities, and the energy transition. Trained as an architect and a graduate of the Politecnico di Milano, she has worked with international firms on sustainable design, urban planning, tourism development, and hospital infrastructure projects. Passionate about design thinking and cross-disciplinary approaches, she has also contributed to the creation of a line of 3D-printed jewelry. She firmly believes in the crucial role of technical information and tech-driven innovation in accelerating the adoption of smart, scalable solutions in the energy and environmental sectors.